Construction Progresses in Grove

Although weather caused major problems with heavy and consistent rain hampering operations, other operations are ahead of schedule and it is still estimated that the new hospital will finish on time, in December of this year.

Launch live webcam.

All storm and sewer projects are complete and the outbuilding area is now ready for framing.

Site grading is 98% complete, utilities are 90% complete, and the following are in process: steel detailing exterior framing, masonry, roofing, interior framing and renovations of the Ambulatory Care Center continues.

The new hospital will have 42 ALL PRIVATE MedSurg rooms, six ICU Rooms 12 private ER rooms, 10 Women’s Health rooms, 4 operating rooms, one Endoscopy rooms 12 all private Pre-Post-Op Rooms and five recovery bays.

Other enhancements will include Electronic Documentation and Automated medication dispensing system targeting patient safety and operational efficiency and an enhanced hearth catheterization lab.


[Click here to view groundbreaking video]

Grove Construction May 2009

Grove Construction

The INTEGRIS Grove General Hospital Foundation is very close to meeting the goal for their $5 million capital campaign to help build the new hospital. All donations will be spent in Grove on the hospital building fund project. If you would like to help meet the goal, call (918) 787-3464 or visit this site.



November 09
What's a Pain Management Doctor?
Culinary Delights-Baking with Agave Nectar
Intermediate Computer (4 day) TAL
November 10
Red, Orange, Green...Colorful Holiday Side Dishes
INTEGRIS Surgical Weight Loss Seminar
November 11
Healthy Heart Walkers Spanish Club
more...

Become a preferred member to gain access to "members only"
events.

It's Free!

Learn More.

Visit our Web Nursery
 
 
INTEGRIS Grove General Hospital
1310 S. Main
Grove, OK 74344
(918) 786-2243

INTEGRIS HealthLine
(888) 951-2277